Swimming pool wall bracing.
This is the third update for the underground basement swimming pool which is being constructed in Wimbledon, London. The quadlock swimming pool wall have now been finished with all the

Pool wall construction begins in London basement pool
Work begins for the pool wall construction on a twin depth basement swimming pool in London. The walls are being constructed using the Quadlock Insulated Concrete Form-work (ICF) system and

New build basement swimming pool
Site excavation work has started on a new build basement swimming pool in London. The pool will be 20 meters in length and will have 2 depths with sloped riser

Slatted thermal pool cover installed and tested in Pershore
A recently completed project in Worcestershire was a new build fully insulated deck level pool. It benefited from the latest energy saving technology in the automated plant-room and a remote controlled

Poolside steam room.
A poolside steam room located at the end of a new build basement swimming pool in London. A steam room is popular addition to many of the new build swimming

School overflow pool commissioned
A new build school overflow pool has been commissioned by Brookforge Poolbuild engineers. Working along side the council architects and builders, Brookforge helped with the design and build on this