Plant Room Pipework Installation, New Forest
Plant Room Pipework Installation Plant room pipework is installed before the floor is screeded. The first stages of a plant room installation revolves around the placement of the suctions and
PoolBuild Journal
News, inspiration and insights from the world of bespoke swimming pools.

Plant Room Pipework Installation Plant room pipework is installed before the floor is screeded. The first stages of a plant room installation revolves around the placement of the suctions and

Stainless steel mesh is fixed to all internal faces to allow rendering. The slab is insulated prior to screeding.
[slideshow id=27] Reinforced concrete slab designed to withstand the force of a large volume of water. The following day, construction of the pool shell can begin. It doesn’t take long

With the Quad-Lock structure supported, the central void is filled with concrete forming the pool shell, balance tank and steps. For more information regarding new builds or renovations, please contact
[slideshow id=26] The Romsey project is making good progress. The starter bars have been fixed to the slab, and the construction of the pool and balance tanks walls has begun
[slideshow id=25] We have just started a new project near Romsey, Hampshire. We are constructing an ICF pool inside the existing liner pool shell. The Shell, however, cannot be relied