Finished Infinity Swimming Pool

Mirrored infinity swimming poolAn infinity swimming pool in the stunning surroundings of the Chilterns, an area of natural beauty, has been completed.

This infinity swimming pool is positioned on a hillside overlooking the valley below with uninterrupted views of rolling countryside.

Brookforge worked alongside the local landscapers to construct this impressive 19m x 4.5m infinity pool which is to be used all year round. The pool benefits from an automatic thermal slatted cover which helps minimise heat loses when the pool is not in use.

Read More…

Swimming Pool Plant Room Installation

Cliff side infinity pool

Cliff side infinity pool

Brookforge pool engineers recently helped complete a swimming pool plant room installation for a cliff edge pool in Salcombe.

The pool was built and tiled by a local pool company and Brookforge took over to install all the pool shell fittings and install/test/commission the highly automated pool plant room.

Working directly for the owner; our engineer worked long hours with several late nights to get this highly automated swimming pool plant room up and running within 6 working days.

Read More…

New Build Outdoor Pool

New Build Outdoor Pool

New Build Outdoor Pool Construction

Work has begun on a new build outdoor pool in the the Chilterns near High Wycombe. The swimming pool has been designed by liaising direct with the clients and the initial pool slab has been constructed by local contractors using the drawings and structural calks provided by Brookforge.

The reinforced concrete slab had a 5 days to cure before we could start on the construction of the pool walls at the start of this week. The initial pool shape was marked and had track for the walls cut to size. The Quadlock walls are then constructed in the track and the size and feel of the pool begins to take shape. Once the first course is complete the pool position, location and proportions are double checked and squared up. Now the pool location is finalized the pool wall vertical steal are drilled and anchored into the pool slab and the next courses can fly up within the space of 2 days. Read More…

New design outdoor pool completed

design outdoor pool

A new design outdoor pool has been completed by our in house designers.

Working directly with the customers; our project manager has finalized the designs for this unique pool.

This bespoke swimming pool is ready to go from paper drawings to being constructed onsite over the next 3 weeks.

The pool will be constructed using the Quadlock insulated concrete formwork and will be carried out by our in house team of pool builders. The initial groundworks and pool slab has been completed by the customer’s landscaper by following the installation drawings provided by our designers and structural engineer. Read More…