Brookforge Swimming Pool Build

Pool Structure Complete

Its the six day on site and the pool structure is complete. After a successful concrete pour the previous day the walls are solid and we can start to remove the bracing and shutter boards.

Whilst the braces are being removed suction and return pipework is installed back to the plant room before the block and beam floors are completed throughout the pool building.

This phase of the pool build is now complete, with the pool structure in place we will return to site once the pool building has been erected around the pool.

On our return we will mesh / render the pool walls then spray tank the pool shell in preparation for tiling.

More updates to follow>>

 