It’s the fifth day on the new pool build and we’re ready for concrete! The insulated concrete form-work we use for our swimming pool shells requires the concrete to be pumped in (via a concrete pump) in a loose liquid form.

Usually pumped via a long boom it means we can reach even the hardest to reach areas and can ensure consistency through the entire pour. Any air pockets are removed with vibration which happens throughout the pour with the use of hand held concrete pokers.

In a matter of a few hours the reinforced concrete pool shell is complete and will begin to cure over night. By the following morning (day 6) the concrete has cured enough that we can begin to remove the the bracing and in the subsequent days it will strengthen further.

Whilst the braces are being removed suction and return pipework is installed back to the plant room before the block and beam floors are completed.

 