Brookforge Swimming Pool Build

New Forest: Concrete Pour

reinforced concrete pool lid being poured
20121128-174308.jpg
Pouring concrete to form a lid over the balance tanks and cover pit

Today we have successfully poured 52 cubic metres of concrete to form the walls, balance tanks and cover lid. As this post goes live, the concrete is curing; resisting the low temperatures with double sided insulation. This stage is a key development within the project and could not be achieved so quickly with alternative pool construction methods.

[12-150]