Final Stages of Pool Commissioning
With the tiling and grouting now complete, all suction and return fittings have been carefully installed into the pool shell. This marks a key milestone in the construction process, allowing us to begin filling the pool with water. The filling process is carried out gradually over several days to ensure every stage is closely monitored for any signs of leakage or imbalance.
Once the pool reaches its full water level, we move on to the commissioning phase. This involves activating the circulation system and thoroughly testing the plant room equipment—including the pumps, filters, heaters, and chemical dosing units—to ensure everything is functioning exactly as it should.
At this point, the water is continuously circulated, filtered, treated, and heated to maintain optimal swimming conditions.
This particular pool also features integrated waterfalls built into a stunning feature wall. These elements are tested and balanced as part of the final setup to ensure they function correctly and enhance both the aesthetics and experience of the space.
Over the next few days, the pool water will gradually reach a comfortable, stable temperature. During this time, chemical treatment levels are carefully monitored and adjusted as needed to confirm that the system is running efficiently and safely.