Hydrotherapy Spa Tiled, East Sussex

The tiling for the Hydrotherapy Spa has been finished, all that remains are the finishing touches to complete the surround. The spa comprises four separate seats and an air massage bed in the middle. There are both air and water jets, and colour changing lights that contribute to the sensory experience.

If you are interested in having a Hydrotherapy Spa constructed, why not get in touch here to discuss your options.

Setting Out Hydrotherapy Pool, East Sussex

Accuracy is checked at regular intervals

Brookforge have undertaken a new project at a school which educates children with disabilities. We are constructing a specialist hydrotherapy pool which will be both stimulating and relaxing for its users; the older children. The pool will include a series of lights and jets, and will feature an air massage bed. For more information on our construction services, get in touch here.

Refurbishment Project: Tiling begins, Cheltenham

Mosaics are fixed to tanking

Tiling has begun at our local site, a refurbishment project to both house and modernise a dated, outdoor pool. The previous tiles have been removed, the shell has had its depth increased and has been tanked. The tile adhesive used is a rapid curing, water resistant product. More about the adhesive can be found here.

New Forest: Concrete Pour

20121128-174308.jpg

Pouring concrete to form a lid over the balance tanks and cover pit

Today we have successfully poured 52 cubic metres of concrete to form the walls, balance tanks and cover lid. As this post goes live, the concrete is curing; resisting the low temperatures with double sided insulation. This stage is a key development within the project and could not be achieved so quickly with alternative pool construction methods.